Major progress as Athlone main drainage tunnelling works now complete
Information below is relevant until further updates are provided here or on our Supply and Service Updates section
The Athlone Main Drainage Scheme is moving towards completion, with all tunnelling works now fully finished and reinstatement works underway across the town. Works along The Quays have also been completed, marking another milestone in the delivery of this critical project.
At Golden Island, the pumping station shaft construction works are fully complete, with mechanical and electrical installations progressing well. The control building for the pumping station is also substantially complete, with only final fit-out works remaining. The Coosan West Pumping Station is also now in operation, providing enhanced wastewater management capacity for the area. The project remains on schedule for completion this year, with flows set to be turned into the new sewer network by October.
Cross-connection works between the existing and the new network are ongoing at various locations around the town. The Strand Carpark will now be reopened in October. This extension will allow the project team to complete works and demobilise safely, minimising the need for future disruption in the carpark.
The Athlone Main Drainage project team will also be carrying out public realm enhancements on Custume Place, which were designated under the Church Street Improvement Works. These works, which are expected to commence in October, will further revitalise the area, creating a more attractive space for the community.
Commenting on the progress, Uisce Éireann Portfolio Manager Eunan Canavan said: ‘We are grateful to the community for their continued patience as we reach the final stages of this transformative project. The Athlone Main Drainage Scheme will significantly improve the capacity and resilience of the wastewater infrastructure, ensuring Athlone is well prepared for future growth and development, while also reducing the risk of sewer flooding, improving the water quality in the River Shannon and supporting a cleaner, healthier environment.’
The Athlone Main Drainage Scheme is one of Uisce Éireann’s largest projects to date, representing an investment of €114m. The project involved the construction of new pumping stations at Golden Island and Coosan West, and almost 3km of new large trunk sewers. The existing under-performing pumping stations and pipework will be decommissioned. Combined sewer overflows have been eliminated at six locations along the River Shannon and replaced by two new stormwater overflows designed to meet current licencing standards, improving water quality, and protecting the environment.
Works have taken place at a number of locations across Athlone including Golden Island, West Bank (The Quay), West Side, Abbey Road, Coosan West, The Strand, Burgess Park, Payne’s Lane, and two separate tunnelled crossings under the River Shannon. The new sewers were installed using trenchless technology, meaning that a significant proportion of the construction took place underground without the need for open-cut excavation.
Uisce Éireann is committed to keeping customers informed across multiple platforms 24/7 and we encourage customers to engage with us through our website, X channels @IWCare and @IrishWater, on Facebook and LinkedIn and through our customer care helpline which is open 24/7 on 1800 278 278.
Uisce Éireann has a free text service, providing real-time updates for local issues. Customers can sign up with their Eircode and mobile number at www.water.ie
Previous Updates
Uisce Éireann is commencing works to upgrade the water network in Athlone, to support future development within the Midland’s town. The project will improve the capacity and performance of the existing water network.
The works involve the upgrading and upsizing of over 2.5 km of water mains at Cartrontroy Road, Coosan Road and Cornamagh Road and will be carried out by Coffey Construction on Uisce Éireann’s behalf. Construction works are due to commence at the start of August and will take approximately six months to complete. The project will be carried out in phases to minimise disruption to the local community.
Separately, design stage works to upgrade the trunk water main connection to Annagh Reservoir will soon commence along the Ballymahon Road across the Athlone Bypass/N6 Road Junction and in the vicinity of Connamaddy National School. Site investigations for this part of the project will begin this month, and the works are being carried out by Ward & Burke Construction.
Commenting on the benefits of the upgrades to the town of Athlone, Padraig Hanly, Portfolio Manager with Uisce Éireann, said: "These upgrades will ensure that the water network is fit for purpose to support sustainable growth and development while also improving the resilience of the drinking water network enabling communities to thrive. We’d like to thank the people of Athlone in advance for their patience and support as we carry out these critical works.”
These vital upgrades are being delivered through Uisce Éireann’s Growth and Development Programme, a national programme of targeted investment to increase the capacity of water and wastewater infrastructure to enable social and economic growth, including the delivery of essential housing. We commit to keeping the local community updated as the details of this project are finalised.
Uisce Éireann is committed to keeping customers informed across multiple platforms 24/7 and we encourage customers to engage with us through our website, X channels @IWCare and @IrishWater, and through our customer care helpline which is open 24/7 on 1800 278 278. We have launched a free text service, providing real-time updates for local issues. Customers can sign up with their Eircode and mobile number at www.water.ie
For further information about the project, please visit our dedicated project webpage.
Water Service Updates
Sign up for our free text service to be kept informed of water outages and works in your area.